How it works
For each line set three columns: expected, actual and variance, in euros and as a percentage. The comparison is made on the same period: October with October, the first ten months with the first ten months.
On revenue a positive variance is good news, on a cost the opposite. To avoid confusion many write «favourable» or «unfavourable» instead of the sign.
An example
An engineering firm of 25 people, October:
| Line | Expected | Actual | Variance |
|---|---|---|---|
| Project revenue | 210,000 | 192,000 | −18,000 |
| External collaborators | 24,000 | 19,000 | −5,000 |
| Staff | 118,000 | 121,500 | +3,500 |
| Software and licences | 6,000 | 6,400 | +400 |
| Margin for the month | 62,000 | 45,100 | −16,900 |
Revenue is €18,000 lower because a milestone slipped to November. Collaborators cost less for the same reason. Staff, on the other hand, went up because of an early hire: €3,500 that will not come back in November.
And in cash
The same comparison can be made on what comes in and goes out. Here variances are of another kind: often they are not more or less money, but money early or late. The slipped milestone is worth €18,000 less revenue in October and, if the customer pays at 60 days, €18,000 less received in November, arriving in December instead.
That is why it pays to read the two comparisons together: the accrual one tells you whether the company earns what was planned, the cash one whether the money arrives when it is needed. The second is made against the cash forecast frozen at the start of the month, not the one updated afterwards.
Common mistakes
- Dividing the annual budget into twelve equal parts: months with holidays, thirteenth-month pay or tax advances always look off track.
- Comparing an accrual-basis budget with cash-basis actuals, or the other way round.
- Looking at a hundred lines: about ten are enough, with a threshold beyond which the variance must be explained.
- Not writing down why: in six months nobody remembers what had slipped.